2016 GIBSON ISLAND TURNAROUND

GITA16 2016 Gibson Island Turnaround
 
Portal  HomeHome  CalendarCalendar  FAQFAQ  SearchSearch  MemberlistMemberlist  UsergroupsUsergroups  RegisterRegister  Log in  

Share | 
 

 New Published: Execution Strategy Procedure and Turnaround Management Plan - Rev0.1

View previous topic View next topic Go down 
AuthorMessage
Admin
Admin
avatar

Posts : 73
Join date : 2015-11-26

PostSubject: New Published: Execution Strategy Procedure and Turnaround Management Plan - Rev0.1   Fri Nov 27, 2015 7:46 am

Refer to your desktop link to view procedure.

Strategy:
Noun
A plan of action designed to achieve a long-term or overall aim.
Synonyms: master plan, grand design, game plan, plan of action, plan, policy, proposed action, scheme, blueprint, program, procedure, approach, schedule…

Purpose:
This document outlines the strategies established to execute a safe, effective (quality) and efficient (tool-time) Turnaround—Gibson Island 2016—to meet the key deliverables.
The Execution Strategy is an integrated approach to developing the Turnaround Management Plan, consisting of individual Stakeholder Strategies and Functional Plans. Its purpose is to assist with developing an overall Turnaround Project Plan (aka Schedule) supported by a DSM (Dynamic Scheduling Methodology).
When formally established, the Execution Strategy identifies how all work will be executed—which activities, when, where, and by whom—with the least amount of risk.
A series of workshops (brainstorming sessions) will be scheduled to establish Stakeholder Strategies and Functional Plans, which will then be incorporated into the overall Turnaround Management Plan by the Planning & Scheduling Team.
Key deliverables are established by the Steering Committee (or key Stakeholders, as directed by the Turnaround Manager), followed by a formal workshop session to define assumptions, identify constraints, and mitigate risk for the various Stakeholder Strategies (e.g., Decommissioning, Materials Management, Inspection, Safety, QA/QC, Environment, Administration) and Functional Plans (e.g., Communication Plan, Mobilization Plan, Evacuation Plan, Change Management, Security Plan, Fatigue Management Plan).
Once the Execution Strategy is complete (T-35 Days) the Schedulers can finalize the Turnaround Project Plan, using strategic, dynamic scheduling to optimize resources and time in Primavera™ P6; while Stakeholders can prepare to support the Turnaround Project Plan with implementation (orientation, training, practice), e.g., tools, materials, safety, consumables, trailers, timekeeping, etc.
Back to top Go down
View user profile http://gita16sto.forum-board.net
 
New Published: Execution Strategy Procedure and Turnaround Management Plan - Rev0.1
View previous topic View next topic Back to top 
Page 1 of 1
 Similar topics
-
» Project Procurement Management Plan
» Annual Procurement Plan
» RuleII - Procurement Planning & Budgeting
» Building Management and Security
» Change of manner of execution of infra projects.

Permissions in this forum:You cannot reply to topics in this forum
2016 GIBSON ISLAND TURNAROUND :: GITA16 STO Forum :: News-
Jump to: